Step 1- We had to get the cabinet from Steelville
MO to Union. When we got to the location to pick up the cabinet a older man came out to tell us that we couldn't pick it up. He said that it was delivered with a crane. Jake and I says that if two guys and a truck can not do it that we don't mess with it.
Step 2- Was to store the cabinet.
Step 3- Was that after the driveway was paved to move the cabinet and mast back. Instead of keeping the mast on the ground, I figured that it would be better to set it up right.
Step 4- Was to rewire it to meet our standards.
Step 5- Was to wire the Power Transfer Relay. I used a ANL-2 relay. This relay is a 110Vac relay.
Step 6- Was to install the transformer and battery charger!
Step 7- Heres the searchlight terminals.
Step 8- To install a Union Switch and Signal company DT-10 timmer relay. This relays is being used to switch the indications.
Step 9- The batteries are installed, and the water levels are within the OK range. This has to be checked every month.